What BS 7671 Amendment 4 Means for Your Home in 2026

A plain-English guide to BS 7671 Amendment 4 (2026) for UK homeowners: what changed, what it costs, and when it starts to appear on your electrician's estimates.

BS 7671 Amendment 4 was published on 15 April 2026, and the previous version is withdrawn on 15 October 2026, from which point new work is designed to it. It widens 30mA RCD protection to AC lighting circuits in dwellings, broadens where arc fault detection devices are recommended, pushes surge protection into more homes, and introduces Chapter 57 covering solar, battery storage, and bidirectional EV charging. Existing installations do not need retrospective upgrading.

Key takeaways

  • Published 15 April 2026 and usable straight away. The superseded version is withdrawn on 15 October 2026.
  • 30mA RCD protection now extends to AC lighting circuits in dwellings, closing the last gap left by Amendment 2.
  • New Chapter 57 governs solar PV, battery storage, and bidirectional EV chargers as one coherent ruleset.
  • Nothing is retrospective. Your existing installation does not become non-compliant on 15 October 2026.
  • A missing AFDD produces a C3 observation on an EICR, which is advisory and does not fail the report.

Every few years the IET publishes an update to the UK Wiring Regulations, BS 7671. The current version is the 18th Edition, published in 2018. Amendment 4 to that edition was published on 15 April 2026 and can be used straight away. The superseded version, BS 7671:2018+A2:2022+A3:2024, is withdrawn on 15 October 2026, so from that point new work is designed to Amendment 4.

Most homeowners never read a wiring regulation, and rightly so. What matters is what changes on your invoice, on your consumer unit label, and on the paperwork you get when the electrician leaves. Here is the short version, in plain English.

What is BS 7671 Amendment 4?

Amendment 4 widens the safety envelope in three main directions: more circuits get 30 mA RCD protection, more circuits get arc fault protection (AFDDs), and homes with batteries or solar have a proper set of rules for the first time (the new Chapter 57 on prosumer installations). Surge protection (SPDs) becomes standard on more residential installs, and the treatment of Power over Ethernet (PoE) gets tidied up.

None of it makes older installations illegal. What it does mean is that any new design, any consumer unit change, and any rewire from October 2026 will be built to the widened rules.

What changed for RCD protection on lighting?

Amendment 2 (2022) already required 30 mA RCD protection on nearly every final circuit. Amendment 4 closes the last gap: AC lighting circuits in dwellings now also fall in scope.

What this means for you: if you’re having a consumer unit change or a partial rewire, expect an RCBO on the lighting circuits (an RCBO is a single device that combines the overload protection of an MCB with the earth-leakage protection of an RCD). Most modern consumer units are already built this way, so the change is invisible on many jobs.

Are AFDDs now required in homes?

An AFDD listens for the electrical signature of an arcing fault, the sort that starts fires in loft spaces and behind sockets. Amendment 4 broadens where AFDDs are recommended in dwellings.

In practice, an AFDD costs roughly 3 to 4 times what a standard RCBO does, so this line item is visible on an estimate. You are entitled to ask your electrician which circuits carry AFDDs on your job and why, and to opt for more coverage than the minimum if you want to.

Do you need a surge protection device?

An SPD protects the wiring and connected appliances from voltage transients, typically caused by a nearby lightning strike or a switching event on the network. Amendment 4 pushes SPDs into more residential installs by default.

A whole-home SPD sits inside the consumer unit and adds around £100 to £250 to a consumer unit change, depending on the device and how the board is arranged. SPDs also have a service life of roughly 10 years, so they get replaced on a rolling basis at each EICR or CU refresh.

What does Chapter 57 cover for solar and battery?

Amendment 4 introduces a dedicated chapter for “prosumer” installations, which is the technical name for homes that both consume and generate electricity. This covers:

  • Solar PV
  • Stationary battery storage
  • Bidirectional EV chargers (V2H, V2G)
  • Backup generators

The chapter formalises how these systems interact with the grid connection, when they can and cannot island (run in isolation from the grid during a power cut), and what protection they must have. If you are having a solar-plus-battery install or considering a V2G charger, this is the ruleset your installer works to. See our EV chargepoint grants post for the grant landscape, and our EV charger installation page for our own service.

What changed for Power over Ethernet?

Home cabling for smart home devices, IP cameras, and access points is often powered over the same Cat6 cable that carries the data. Amendment 4 updates the guidance on cable ratings and installation methods for PoE to reflect the higher currents modern PoE++ standards can deliver.

Only relevant if you’re planning structured cabling for a self-build or a major refurbishment. If your home has one wireless router in the hallway and that’s it, nothing changes for you.

What else changed in Amendment 4?

  • Updated cable colour and marking rules for prosumer installations
  • Tightened guidance on external influences (temperature, moisture, mechanical stress) for outbuilding and garden circuits
  • Clearer language on labelling and documentation for the “as-fitted” record

When does Amendment 4 come into force?

Three dates to know:

  • 15 April 2026: Amendment 4 published
  • 15 October 2026: the superseded version is withdrawn. From this point any new installation, consumer unit change, or rewire is designed and certified to A4.
  • Existing installations: no requirement to bring them up to A4 retrospectively. Your EICR is still assessed against the standard your installation was designed to, with C3 “improvement recommended” observations for anything that would fail the current rules.
ChangeWhat it affectsTypical added cost
RCD on lighting circuitsNew consumer units, rewiresUsually none, RCBO boards are already standard
Wider AFDD recommendationNew designs, some rewires3 to 4x an RCBO per protected circuit
Surge protection (SPD)Consumer unit changes£100 to £250 per board
Chapter 57 (prosumer)Solar, battery, V2G installsDesign overhead, not a fixed cost
PoE cable ratingsStructured cabling, self-buildsSpecification only

Cost guidance as of July 2026 and indicative only. The superseded version is withdrawn on 15 October 2026. Amendment 4 is not retrospective.

Will Amendment 4 make your EICR harder to pass?

Not automatically. C1 and C2 observations, the ones that produce an Unsatisfactory result, are about danger. A missing AFDD does not create a C1 or C2; it produces a C3 “improvement recommended”, which does not fail the report. See our EICR cost guide for the full observation code breakdown.

What may change is the shape of the remedial estimate you get after an Unsatisfactory EICR. If your installation is being brought forward to modern standards anyway, your electrician will spec Amendment 4-compliant kit as the default. You always get to choose the level of upgrade you want.

What should you ask your electrician?

When you next get an estimate for a consumer unit change or rewire in Wiltshire, three good questions:

  1. Is this estimate designed to Amendment 4 or Amendment 3?
  2. Which circuits carry AFDDs, and can I opt for more coverage?
  3. Is an SPD included, and if so which type?

Any NICEIC or ECA approved contractor will answer all three without hesitation. Every job we estimate from October 2026 onwards is designed to A4 by default, with any deviation clearly flagged and priced.

Get an estimate

See our house rewire page or EICR testing page for our own domestic services, or contact us for an estimate on your property.

Service areas: Nulectrics is based in Chippenham, Wiltshire. We cover domestic work across Chippenham, Corsham, Calne, Melksham, Devizes, Trowbridge, Bath and the surrounding area, and commercial work UK-Nationwide.

Frequently asked questions

Do I need to upgrade my electrics because of Amendment 4?

No. The superseded version is withdrawn on 15 October 2026. Amendment 4 is not retrospective. Your existing installation does not become unsafe or non-compliant. Where it matters is on your next consumer unit change, rewire, or new circuit, which will be designed to the updated standard by default.

What is an AFDD and do I need one?

An arc fault detection device detects the electrical signature of an arcing fault, the type that starts fires behind sockets and in loft spaces. Amendment 4 broadens where they are recommended in dwellings. They are not universally mandatory, and you can choose more coverage than the minimum if you want it.

How much does a surge protection device cost?

A whole-home SPD fitted inside the consumer unit typically adds £100 to £250 to a board change, depending on the device type and how the board is arranged. SPDs have a service life of roughly ten years, so they are replaced periodically at an EICR or during a later consumer unit refresh.

What is Chapter 57 in BS 7671?

Chapter 57 is a new section introduced by Amendment 4 covering prosumer installations, meaning properties that both consume and generate electricity. It brings solar PV, stationary battery storage, bidirectional EV chargers, and backup generators under one consistent set of rules for grid interaction, islanding, and protection.

Will Amendment 4 make my EICR fail?

Unlikely. EICR results turn on C1 and C2 observations, which indicate actual danger. Items that only fall short of the newest standard usually attract a C3, meaning improvement recommended, which does not produce an Unsatisfactory result. Your installation is assessed against the standard it was designed to.

When does Amendment 4 take over from Amendment 3?

Amendment 4 was published on 15 April 2026 and could be used from that day. The superseded version, BS 7671:2018+A2:2022+A3:2024, is withdrawn on 15 October 2026, which gives the industry a six month transition. From that point new work is designed and certified to Amendment 4. Work designed before the changeover can still be certified against the earlier version.

Does Amendment 4 affect EV charger installations?

Yes, mainly through Chapter 57 where the charger is bidirectional and can export to the property or grid. Standard one-way 7kW home chargers are largely unaffected. If you are considering vehicle to home or vehicle to grid capability, Chapter 57 is the ruleset your installer now works to.